All News

Work on the electric system in the area North of Rio Grande City, South of Bruni, South of Laredo and East of Zapata will result in two 45 minute power outages on Thursday, February 6, at some point between 9 a.m. and 5 p.m.

 

One of the 45 minute outages will happen in the morning, before work begins, and the second 45 minute outage will happen in the afternoon when work is complete. Because of the fluid nature of the work, we are unable to provide impacted members with exact times the outages will occur.

 

This project involves replacing poles that serve the substation, and power must be cut before work begins and once the work is complete.

 

All members who will have meters impacted were notified with a phone call and / or email. If you would like to add an additional phone number or email to your account for outage notifications, please contact us at Info@MedinaEC.org.